1. Crushing Section:-
Raw materials including limestone, clay, coke
etc are crushed in separate crushers and stored
automatically in separate silos.
2. Storage & Proportioning:-
The raw materials are extracted in required proportions
from the silos by table feeders and conveyed to
the raw milling section.
3. Raw Milling
:-
The raw mix is ground into a Ball Mill (or other)
to the required fineness producing Raw Meal, this
is transported for Homogenizing
4. Blending & Homogenization :- The raw meal is homogenized in the
blending silos, and is stored automatically in
storage silos for feeding to the kiln.
5. Palletizing
& Burning:- The nodules are made
into a nodulisers and charged into the kiln for
burning. The clinker after discharge is stored
in the clinker yard through deep Bucket Elevator.
6 .
Clinker / gypsum crushing, storage & proportioning:
- Clinker & Gypsum
after crushing stored into the hoppers and extracted
in the desired proportion with the help of table
feeders and transported to the Cement mill Hopper.
7. Cement
Milling: - The clinker & Gypsum mix
is ground in the cement mill to produce cement.
8. Storage
& Packing:- The cement is stored
in cement silos and aerated, tested and packed
for dispatch.
Raw
Materials |
|
1. Limestone T.C.-90%, CaO - 50% min. (MgCO3
< 5%) |
| 2.
Clay Al2O3 - 14-18% (SiO2 - 60% max.) |
| 3.
Coke Calorific value: 4000 K Cal/Kg min.
|
| 4.
Gypsum CaSO4.2H20- 75% min |